Mon – Fri: 7:30 – 17:00
01865 727159

Christ Church – Cathedral Lighting – Phase III

PROJECT DESCRIPTION

 

Acting as the main contractor on this phase of works, we have started on site having issued our Construction Phase Plan.

Site setup consisting of  protection to Cathedral artifacts, welfare facilities including hand sanitising stations and access equipment(scaffolding) has been carried out and works are underway.

We’re currently installing both FP200 and MICC (fire resistant) cable along the clerestory cable containment system, between the new LED light fittings final location’s in the Latin Chapel, North Aisle, Lady Chapel, South Transept, Central Tower and the power and control devices that are to be installed in a serviceable location.

Final designs of the Mike Stoane luminaires have been submitted  for approval to put into manufacture.

Principal Designer – Purcell

CDM Consultant – Andrew Alder Associates Ltd

Lighting Design – Sutton Vane Associates

Electrical Consultant – CBG