Mon – Fri: 7:30 – 17:00
01865 727159

University College Oxford – Lighting update

The Library at 10 Merton Street – Completed winter 2017

After a temporary let to the Blavatnik School of Government, University College took the Library at 10 Merton Street back into the fold.

Part of the works we undertook involved changing the of use of some of the rooms, so we updated the lighting in the ground floor corridors and offices. We also updated and installed architectural lighting in the entrance lobby and carried out an essential lighting and power upgrade to the main library, where we installed LED tape light, chandeliers and bespoke luminaires.

Read more

Christ Church – Cathedral Lighting – An ongoing Project

PROJECT DESCRIPTION

Back in 1998 we installed the Cathedral lighting at Christ Church. In 2019 we we were brought back in to upgrade and update the ageing system, which was no longer suitable for the environment. The solution was a complex phased lighting refurbishment.

Phase I works involved isolating and removing the North Aisle capital lights and the North Transept Clerestory lights before installing new LED lighting along with emergency lighting. We installed bespoke enclosed LED tape around the capitals of the North Aisle, high powered LED spots on the Clerestory of the North Transept, converted the Stall lighting in the Latin Chapel and installed high powered spot lights in the Watching Loft.

We carried out wiring using MICC cables and FP200 cabling, predominantly installed around the containment route on the Clerestory where a special harness and equipment was required for mobility. All the new lighting is scene functionable, with every circuit Bluetooth controlled via the Cathedral operator’s tablet.

Phase II works involved isolating and removing the lights in the South Aisle, the Choir Stalls, the Nave and the underside of the Organ Loft, then installing modern lighting to replace them. We incorporated the new lighting into the existing emergency lighting system using change over and hold off relays, and the same type of LED tape was installed around the capitals of the South Aisle.

We installed high powered spot lights on the Clerestory level of the Nave and recessed spot lights to the underside of the Organ loft. And we upgraded all the Nave Choir stall lighting from hot, inefficient halogen lamps to cool, high powered LED chips, with incorporated Bluetooth dimmer modules as an integral part of the circuitry.

Read more

Christ Church – Kitchen Works

PROJECT DESCRIPTION

Installing new Mains Infrastructure – Completed 2017

We were appointed by Christ Church to supply and install a new submain and distribution system to the kitchen’s existing electric system.

The kitchen range was due for an upgrade from gas to electric, which was going to affect the power consumption of the electrical system thanks to an insufficient existing supply. The work therefore involved installing 2no 240mm2 4core LSFSWA cables from the South Substation, through the grounds of Christ Church via excavations and through the fabric of the building, all the way to the Chef’s office.

The new cable was terminated into a new Panel board, upgrading the whole of the distribution. To avoid disrupting the kitchen, we carried the work out one circuit at a time to ensure the room always had power. We also installed new submain circuit cables to various pieces of equipment.

Read more

Christ Church – Electrical Installation Testing

PROJECT DESCRIPTION

Testing electrical installations – Completed 2018

We were appointed by Christ Church to carry out electrical installation condition reports, essential periodic testing. The work involved close liaison with the Clerk-of-the-works department to programme and arrange varous areas for sequencing.

The building’s sheer size means testing takes just over a year to complete, and we have to work closely alongside every department at Christ Church to ensure there’s minimal disruption.

The kitchen is particularly busy, as is the catering department, and the testing work was about as tight and complex as it gets. We only had a three hour daily slot in which to do the tests, but our lead test engineer programmed in all the works with the C.O.W and Head Chef to a satisfactory level.

Read more